Professional Practice Architecture Practice Test

Disable ads (and more) with a membership for a one time $2.99 payment

Prepare for the Professional Practice Architecture exam. Study with flashcards and multiple-choice questions, each featuring hints and detailed explanations. Ace your exam with confidence!

Each practice test/flash card set has 50 randomly selected questions from a bank of over 500. You'll get a new set of questions each time!

Practice this question and more.


What signifies the primary authority of an architect over the contractor during construction?

  1. Approved Construction Documents

  2. Architect's Service Agreement

  3. Change Orders

  4. Supplementary Specifications

The correct answer is: Change Orders

The primary authority of an architect over the contractor during construction is signified by change orders. Change orders are formal documents that reflect any changes to the original construction contract, which must be agreed upon by both the architect and the contractor. When changes arise—whether due to design modifications, unforeseen site conditions, or other factors—the architect plays a crucial role in drafting and approving these change orders. This authority allows the architect to direct the contractor on how to proceed with modifications, ensuring that the construction aligns with the design intent and meets regulatory standards. Additionally, the architect's approval of change orders directly impacts project timelines, costs, and coordination among various stakeholders, reinforcing the architect's leadership role in the construction process. While approved construction documents establish the baseline for the project, the architect’s service agreement outlines the relationship and services provided, and supplementary specifications augment the primary documents, none of these provide the same direct authority over changes during construction as change orders do.