What is a common consequence of an Owner making frequent change requests?

  1. Increased project timeline

  2. Higher initial contracts

  3. Decreased Architect fees

  4. Implementation of a different compensation method

The correct answer is: Implementation of a different compensation method

The common consequence of an Owner making frequent change requests is primarily an increased project timeline. Frequent changes often lead to delays as the project team must revisit and revise plans, coordinate adjustments with contractors, and possibly renegotiate timelines with various stakeholders. This extended timeline can result from the need to accommodate design alterations, reassess budgets, and manage rework due to the evolving project scope. While other consequences can arise from frequent change requests, such as increased costs or adjustments to compensation methods, the most immediate and common result is typically the extension of the project timeline. Changes disrupt the flow of work, necessitate additional meetings to discuss the implications of changes, and can require more resources than originally planned, all contributing to a lengthened schedule.