A full-time supervisor hired by the Owner should report technical matters to whom?

  1. Architect

  2. Owner

  3. Contractor

  4. No one; he is the supervisor

The correct answer is: Architect

The supervisor hired by the Owner plays a crucial role in overseeing the construction process and ensuring that it aligns with the project’s specifications and standards. Reporting technical matters to the Architect is appropriate because the Architect is responsible for the design and construction oversight. The Architect possesses the expertise needed to interpret technical details and resolve any design-related issues that may arise during construction. The relationship between the supervisor and the Architect is vital for facilitating effective communication regarding any technical concerns or discrepancies. This collaboration helps to maintain the integrity of the design and ensure that the project adheres to the established performance criteria. In this context, while the Owner ultimately holds responsibility for the project, the supervisor acts as a point of contact for day-to-day technical issues and advancements, which necessitates a clear line of communication with the Architect. This ensures that any technical decisions made during the construction phase are informed by the original design intent and adhere to professional standards.